Fawley Waterside keeps £3.4m support after missing funding deadline
The project could not use its original grant in time after changes to its plans, but Solent Freeport says the same amount has been protected from another funding source.

Fawley Waterside in Hampshire has missed a deadline to use £3.4 million in government seed funding, but Solent Freeport says the development has not lost the money. The same amount has been protected in the Freeport’s capital budget and is expected to come instead from future business rates retained within its tax sites.
The funding was intended to support infrastructure and other projects across the Freeport area. Changes to Fawley Waterside’s plans meant the project could not spend the grant before the government deadline. The Freeport board agreed on April 20, 2026, to redirect the time-limited seed capital to another project able to progress sooner.
The decision was discussed by New Forest District Council’s resources and transformation overview and scrutiny panel on Thursday. Fawley Waterside’s latest plans focus on an employment hub for energy, engineering, maritime and digital businesses on the former power station site, with up to 143,000 square metres of commercial space proposed.
Why the funding changed
Solent Freeport chair Brian Johnson said the board’s decision was intended to put funding with a spending deadline to effective use while protecting Fawley Waterside’s full allocation through another source. He said the organisation remained “fully committed” to supporting the development.
The replacement funding is expected to come from future retained business rates. These are rates raised within Freeport tax sites that can be kept and reinvested in economic growth and development. Solent Freeport has not announced when the money will be available.
How the plans have changed
Earlier proposals included a £2.3 billion development with 1,500 homes, a marina, a primary school and commercial space, with more than 2,000 jobs. Those plans were withdrawn in 2024 after being deemed financially unviable.
The scheme has since been reworked around employment uses. Solent Freeport said it continues to work with the Fawley Waterside team as a new masterplan is developed. Any further funding would be considered against the Freeport’s investment priorities and available resources.
This report draws on information from Daily Echo.